WORKS
Construction Case Study
【BioStyleClinic Osaka】
At BioStyleClinic Osaka, air conditioning equipment is planned integrally according to the usage of the culture room, preparation room, and adjustment room.
This is a CPC construction case that implements cleanliness management and differential pressure control, including equipment inside the ceiling.
● Separate the culture room system from the preparation and adjustment room systems, and organize the air conditioning and ventilation equipment necessary for environmental maintenance.
In cell culture processing facilities, it is necessary to clarify the flow of supply air, exhaust air, and auxiliary exhaust air to maintain a clean environment in each room.
In this case, we have constructed an air conditioning system tailored to the purpose of each room, including equipment within the ceiling.
● HVAC System Diagram